The quantities column in Shift View indicates the actual produced good or total quantity (depends on the user’s preference in view settings) vs the target quantity of the product.

<aside> 🎯 The target is calculated based on the ideal cycle time of the product and planned production time. If during one hour, products with different cycle times are produced, then the target is proportionally adjusted. It is possible to reach the target if availability and performance are both running at 100% – the whole hour is green and has no unplanned stops.
</aside>
In case of stops that are excluded from OEE calculation (e.g., Lunch), planned production time is reduced, reducing the target. Stops that are included in the OEE calculation do not reduce planned production time, and therefore the target is not reduced.
The coloring is based on the OEE targets that have been set in station settings.

Different colors indicate how production is performing against your OEE targets for that station:
Please find more information about Shift View colors here.